Automated Microsoft Project Slip Reports

Every Monday, WebRun opens Microsoft Project, compares each task and milestone against its baseline finish date, records how many days each one has slipped in Airtable, and writes a status report in Notion naming the critical-path items at risk and who owns them.

Runs on WebRun · Strict Lockdown policy
Every Monday at 8:00 AM WebRunorchestrates each step
1 Microsoft Project compare tasks against baseline
2 Airtable record the slip per task
3 Notion write the weekly status report
In short

How do I track which project milestones are slipping?

WebRun opens Microsoft Project every Monday and compares each task and milestone against its baseline finish date. It records the days of slip per task in Airtable and writes a Notion status report naming at-risk milestones, the worst-slipping tasks, and their owners, so delays surface weekly.

  • Slipping milestones are named weekly with days lost
  • Slip accumulates visibly instead of appearing at the deadline
  • Recovered tasks are reported alongside the risks

Built for project managers · PMO teams · construction planners · engineering leads

Step by step

What does WebRun do on every run?

The exact actions WebRun takes, in order - in plain language, so you can adjust anything.

  1. WebRun signs in and gets to work

    Opens project.microsoft.com in a real browser with your saved login - no setup, no API keys.

  2. 1
    Microsoft Project - compare tasks against baseline
    project.microsoft.com
    WebRun in Microsoft Project: compare tasks against baseline
    WebRun opens Microsoft Project to compare tasks against baseline.
    • Open Microsoft Project and load the plan you track
    • Compare each task's current finish date against its baseline finish date
    • Capture the task name, owner, percent complete, and days of slip
    • Flag every milestone whose date has moved and every task now past due
    • Read only. Never change a date, a dependency, or an assignment

    Done when Every task and milestone has its slip against baseline recorded.

  3. 2
    Airtable - record the slip per task
    airtable.com
    WebRun in Airtable: record the slip per task
    WebRun opens Airtable to record the slip per task.
    • Open your Project Tracking base in Airtable
    • Add or update a row per task with owner, baseline date, current date, and days slipped
    • Keep a weekly snapshot column so slip can be seen accumulating
    • Mark tasks that recovered their date since last week

    Done when Airtable holds this week's slip figure for every tracked task.

  4. 3
    Notion - write the weekly status report
    notion.so
    WebRun in Notion: write the weekly status report
    WebRun opens Notion to write the weekly status report.
    • Create this week's status page in your Project Reports space in Notion
    • Lead with the milestones at risk and the days each has moved
    • List the five worst-slipping tasks with their owners
    • Note what recovered since last week so the report is not only bad news
    • Keep it internal. Never send a status update to a client from this run

    Done when This week's status report is published to the internal Notion space.

Run settings

How is each run configured?

Starting pageWhere Chrome opens at the start of each run
project.microsoft.com
ScheduleRuns automatically on this cadence
Every Monday at 8:00 AM
DeliveryHow each run's result reaches you
Status report · Notion
OutputWhat each run produces - A weekly Notion status report naming at-risk milestones and the worst-slipping tasks, backed by an Airtable row per task tracking slip over time.
Text
Setup & safety

Secure by default

Connect once, stays signed in

WebRun signs in once and keeps each session in a persistent environment, so every run picks up right where it left off.

Your credentials stay in your own private environment - WebRun never stores your passwords.
Strict Lockdown

Every action is checked against this policy before it runs.

Domains ALLOWLIST
Typed input ALLOW
Shell command BLOCK
File uploads BLOCK
Runs in a contained environment More on policies
Good to know

Questions, answered

Will it reschedule tasks in my plan?

No. WebRun reads Microsoft Project only. It never moves a date, edits a dependency, or reassigns a task. Replanning stays with your project manager, so the schedule only changes when a person decides it should.

Does the report go to clients?

No. The status report is written to your internal Notion space. WebRun never emails a client or a stakeholder outside your team. If you want an external update, WebRun drafts it and you approve and send it.

What if a task has no baseline?

It is listed separately as unbaselined rather than reported as zero slip, so gaps in the plan are visible instead of quietly making the project look healthier than it is.